China seeks additional guarantees before releasing $6 billion loan for ML-1 ?

By National News Desk

Islamabad: China has sought additional guarantees before placing a USD 6 billion loan on Pakistan’s Main Line-1 (ML-1) railway line as a result of the country’s deteriorating financial status, according to a media report on Wednesday.

China has also suggested a combination of industrial and concessional loans to finance the rail project, against the wishes of Islamabad for “cheapest lending’.’

The question of additional guarantees was posed during the third meeting of the Joint ML-1 Financing Committee held 10 days ago (December 13), the Express Tribune reported, citing official documents.

The senior Pakistani official involved in the negotiations said that China raised the question of additional assurances during the meeting, but did not make it part of the draught minutes shared with Pakistan.

Both countries have not yet signed the draft minutes. The ML-1 project involves the dualization and upgrade of the 1,872 km railroad from Peshawar to Karachi and is a significant achievement for the second phase of the China-Pakistan Economic Corridor (CPEC).

The official said that China raised the question of additional guarantees to explain Pakistan’s financial situation after applying for debt relief from the G-20 countries, which is only for the poorest nations in the world.

The third round of financial negotiations provided more clarification on China’s stance on USD 6 billion in loans for Pakistan Railways’ USD 6.8 billion strategically critical ML-1 project, according to sources in the Ministry of Economic Affairs.

As part of the G-20 debt relief, Pakistan cannot secure costly commercial loans except those allowed under the International Monetary Fund and the World Bank.

The Chinese authorities have proposed that “keeping in view the financial situation in Pakistan so also the conditions laid down by the G-20 regulations for debt suspension, the government of Pakistan may provide additional guarantee mechanism for the loan other than sovereign loan for the ML-1 project”, according to officials privy to the negotiations.

It was surprising for us when China raised the issue of additional guarantees during the meeting, another senior Pakistani official who was part of the meeting said.

In August this year, the Executive Committee of National Economic Council (ECNEC) approved the strategically important ML-1 project worth USD 6.8 billion.

The ECNEC meeting had continued for hardly 20 minutes, leaving many critical issues about financing and technical details unresolved.

Both the sides have reached broad-based consensus on the technical parameters, including bidding documents, according to deliberations that took place in the joint bilateral third financial and seventh technical committee of ML-1 project.

But an early start of construction work on what the official described as “strategically important project” is unlikely after China linked the civil works with prior finalisation of financing mechanism of the single-largest project of the CPEC.

Unlike Pakistan”s expectations of getting the USD 6 billion loan at 1 per cent interest rate, China has proposed a mix of commercial and concessional lending, the sources said.

China maintained that the lending will be both a combination of commercial and concessional loans, according to sources.

The Economic Affairs Ministry had proposed a 1 per cent rate while the Ministry of Railways was inclined to take the mix of commercial and concessional rate, subject to the condition that the average rate may remain lower than 2.38 per cent, sources said.

However, Pakistan was expecting that due to the strategic nature of the project, China would accept its request for 1 per cent interest rate and a grace period of 10 years for repayment of the loan.

China has offered to finance 85 per cent of the project cost with payback period of 15 years to 20 years in biannual tranches. Sources said the Chinese had offered a five years grace period.

Pakistan has asked for up to 90 per cent of financing and was ready to accept a 20 years repayment period, subject to the condition that the grace period should be 10 years.

“The Chinese side proposed that negotiations for financing must be only to the extent of package-1 consisting of USD 2.434 billion and the negotiation for remaining two packages will be undertaken during the implementation phase of package-I,” according to the official documents.

Pakistani authorities pressed for negotiation for the total project cost of the ML-1. China has also offered financing in Chinese currency Renminbi (RMB).

According to the ML-1 framework agreement, the project will be executed in the engineering, procurement and construction mode by Chinese contractors. Under the CPEC framework, ML-1 is the only strategic project being finalised as part of the initial USD46 billion deal.

Sources said that Pakistan’s desire to start work on the package-1 from January 2021 would remain unfulfilled due to delay in finalisation of financing details.

Pakistan had planned to complete the package-I from January 2021 to December 2024 and will cover the construction of a 527-km track between Peshawar, Rawalpindi and Lahore, according to the paper.

The CPEC is part of China”s One Belt, One Road initiative, a global infrastructure development strategy to invest in nearly 70 countries and international organizations. India has expressed concern over the projects as a portion of the CPEC runs through Pakistan-occupied Kashmir, violating Indian sovereignty.

(Inputs from PTI)